Boylesports Birr

Works are scheduled to commence in the coming weeks on extension works to Boylesports in Birr, Co. Offaly.

The scope will involve the extension of existing shop footprint across adjoining structure with the first floor areas of both buildings being converted into Living Accommodation.

Demolition works, involving extensive temporary work, mini piling & steel frame supports will be succeeded by re-roofing and internal fit out of shop and apartments.

Works will be phased to ensure client operations are maintained throughout the overall work schedule of 32 Weeks.

Highline Building Pottery Road

JSD has commenced the extension of the Highline Building on Pottery Road, Dun Laoghaire. 

The glazing of curtain walling to new 3rd and 4th floor is underway at the Highline Development Pottery Road.

Teagasc Ashtown, Co. Dublin

JSD are making good progress on the Teagasc Ashtown project. The structural steel frame and cladding have been erected. 

The structural floor slab will be poured this week. 

The installation of the internal clean room panels and M&E first fix will begin on early next week.

RCSI Fit Out Projects

In the past month, JSD has successfully completed three fit out projects for the Royal College of Surgeons of Ireland on their different campuses. 

All three projects took place over extremely short access windows and all were handed over on time and on budget.

  1. Covid-19 Testing Laboratory, St Stephens Green Campus. Construction and fit out of new testing laboratory including all finishes, lab furniture and M+E. Program: five days.
  1. Extension to Physiotherapy Rooms, St Stephens Green Campus. Demolition and extension of existing physiotherapy rooms including all finishes and M+E alterations. Program: five days.
  1. Finance Offices, Connolly Hospital Office. Strip out, demolition, construction and fit out of six new offices in existing academic building including all finishes, M+E installations. Program: ten days.

Bloom HQ, Mountrath, Co. Laois

JSD has commenced the renovation and fit-out of a shared office space and seminar facility in Bloom HQ, Mountrath, Co. Laois.

JSD will fulfil the role of Main Contactor & PSCS tasked with completing Structural Alterations & Internal Fit-Out of existing buildings including all CSA, Mechanical & Electrical works associated with the project delivery.

The project is scheduled for completion in November 2020.