In the past month, JSD has successfully completed three fit out projects for the Royal College of Surgeons of Ireland on their different campuses. 

All three projects took place over extremely short access windows and all were handed over on time and on budget.

  1. Covid-19 Testing Laboratory, St Stephens Green Campus. Construction and fit out of new testing laboratory including all finishes, lab furniture and M+E. Program: five days.
  2. Extension to Physiotherapy Rooms, St Stephens Green Campus. Demolition and extension of existing physiotherapy rooms including all finishes and M+E alterations. Program: five days.
  3. Finance Offices, Connolly Hospital Office. Strip out, demolition, construction and fit out of six new offices in existing academic building including all finishes, M+E installations. Program: ten days.